Gantt does not show correct dates

When I set the start/end date of a task, if I see it in the gantt view, I cannot see the correct HH:MM, instead I see 00:00

I have reproduced it on try.vikunja


That’s kind of intentional, since the hours won’t be visible anyway in the resolution of the Gantt chart. Not sure what would be the solution here, maybe removing the hours from the display?

While hours won’t be graphically visible, I think that displays the hours when you put the mouse over the task would be useful to understand how much time it took. So in short just fill it with the data instead of 00:00

Hello.
How do I change the color of each task in the Gantt chart view?

In the task detail view, there’s an option to change the task color.